I-94 retrofitting will run past holiday

Published Saturday, August 23, 2008

Work along the westbound lane of Interstate 94, between Evansville and Dalton, should be completed shortly after Labor Day. The work, which started July 7, was necessitated because of mid-panel cracks.

According to the Minnesota Department of Transportation (MnDOT) office in Morris, the distance of 28 feet between concrete joints were found to be too long. The result was mid-panel cracking, in turn causing road faults.

“In order to restore the load transfer, dowel bars are being installed at the location of the mid-panel cracks,” said Dan Kuhn, resident engineer for the Mn DOT Morris office. “Concrete along Interstate 94 is 11 inches thick.”

Brad Cegla, chief inspector for MnDOT’s Morris office, said that between 15 and 25 employees, on a given day, work along Interstate 94 between Evansville and Dalton.

The overall goal of the project is to repair and perform rehab on the damaged concrete.

Comments

The Daily Journal is happy to host community conversations about news and life in Fergus Falls and the surrounding area. As hosts, we expect guests will show respect for each other. That means we don't threaten or defame each other, and we keep conversations free of personal attacks. Witty is great. Abusive is not. If you think a post violates these standards, don't escalate the situation. Instead, flag the comment to alert us. We'll take action if necessary. It's not hard. This should be a place where people want to read and contribute -- a place for spirited exchanges of opinion. So those who persist with racist, defamatory or abusive postings risk losing the privilege to post at all.

Post a comment

(Requires free registration.)

Username:
Password: (Forgotten your password?)

Comment:



© 2008, Fergus Falls Newspapers, Inc.

Boone Newspapers, Inc. | About us | Subscribe | Printing | E-Edition | Contact us | Advertise with us